Authority Name | Action Date | Action |
Final Action Flag |
Authority Comment |
PLANNING BOARD |
02/17/2022 | APPROVED |
No |
RECONSIDERATION (ROAD CONSTRUCTION) (2-17-20220 APPROVED W/CONDITIONS & FINDINGS |
PLANNING BOARD |
12/16/2021 | APPROVED |
No |
PLANNING BOARD APPROVE A SIX-YEAR VALIDITY EXTENSION |
PLANNING BOARD |
12/16/2021 | PENDING |
No |
REQUEST AND RECONSIDERATION GRANTED FOR FUTURE DATE |
STAFF |
11/16/2017 | VERIFIED |
No |
RECORD IMAGING IS COMPLETE |
STAFF |
07/29/2015 | IMAGING |
No |
CERTIFIED PRELIM & TCP-I SET; CASE FILE RETURNED BY LEGAL DEPT. ON 7.14.17 |
STAFF |
12/19/2014 | TRANSMITTED |
No |
File to Legal |
PLANNING BOARD |
12/04/2014 | DENIED |
No |
request for Reconsideration of Rules ((Mistake of Law) |
PLANNING BOARD |
11/26/2014 | APPEALED |
No |
PLANNING BOARD'S DECISION APPEALED TO CIRCUIT COURT |
PLANNING BOARD |
10/02/2014 | APPROVED |
Yes |
70 DAY WAIVER REQUEST RECEIVED ON 5/23/14 |
SDRC MEETING |
06/20/2014 | SCHEDULED |
No |
ON SDRC FOR REVIEW OF VARIATIONS ONLY |
SDRC MEETING |
06/06/2014 | SCHEDULED |
No |
Variation Request |
SDRC MEETING |
05/09/2014 | SCHEDULED |
No |
WITH A VARIANCE & VARIATION |